The photovoltaic system at "H-Campus"
Cliente: Finanziaria Internazionale Investments SGR S.p.A.
Servicios en este proyecto:
- Direzione Lavori generale e specialistica
- Progettazione definitiva
The services provided were the engineering design of the photovoltaic system with a peak power of 1498.20 kWp. This installation serves the supra-regional "H-Campus" Hub of innovative and educational services, which consists of 6 photovoltaic parks:
- Block A – 237.60 kWp
- Block B – 300.30 kWp
- Block C – 376.20 kWp
- Block D – 211.20 kWp
- Block E – 224.40 kWp
- Block H – 148.50 kWp
The project was approved by Decree No 64 of 25/06/2019 of the Veneto Region under the Regional Unified Authorisation Procedure (P.A.U.R.).
Póngase en contacto con Nuestro Equipo
Davide Marchetti
Head of Distributed Generation Business UnitDatos del proyecto
- País
- Italy
- Ubicación
- Veneto
- Año
- 2019 - 2020
- Estado del proyecto
- Finalizado