COMPLETION OF THE PARAMASSI TUNNEL WORKS
The works for the extension of the Paramassi Tunnel on Provincial Road 563 "di Salesei," in the municipality of Rocca Pietore (BL), have been completed. The project, which started in the spring of 2023, involved the extension of the existing tunnel by approximately 40 meters, with the aim of increasing safety and improving the road section's drivability.
DBA followed the project from the early stages, managing the Design, Operational Direction and Safety Coordination, ensuring quality and efficiency at every phase of the construction site.