The Abu Qir Container Terminal
Cliente: Hutchison Ports Red Sea Container Terminals Overseas Limited
Servicios en este proyecto:
- Direzione Lavori generale e specialistica
- Project Management
- Concept Design
The engineering services are related to the design of the Container Terminal of the Abu Qir Marine Port.
The project includes:
- a new container terminal featuring a 1.2 kilometres wharf with a lateral average depth of water over cill equal to -17 mCD and approximately 60 hectares of storage area;
- an access channel and navigation area of -17.6 mCD, as well as a turning basin with a diameter of 700 metres, also at the level of -17.6 mCD;
- a breakwater structure;
The scope of the project covers the following activities:
Marine construction:
the demolition and disposal of existing maritime structures; wharf facilities; miscellaneous installations, including: electrical, water bunkers, etc., and other associated equipment;
dredging operations to be undertaken for the new wharf, access channel, turning basin, and breakwaters; an artificial catchment basin adjacent to the wharf and soil treatment facilities; and additional breakwater structures.
Earthworks:
the removal and disposal of any hazardous materials; the demolition of existing structures; the paving of the access road with road markings; a new entrance and exit gate with gantries and structural equipment; container yard facilities; internal carriageways and connections to the existing road system; additional ancillary works including drainage, HV and LV power supply and distribution, ducting and communication towers, the water supply and lighting systems, including the electrical substations; surveillance, supervisory control and data acquisition (SCADA) system; fire-fighting installations; the workshop and the connected rubber-tired gantry crane (RTGC) maintenance platform; the fuel plant; drainage; improvement of the existing utilities and road connection and provision of a new parking and manoeuvring area for buses; underground conduits and utility holes for the electrical RTGC systems.
Póngase en contacto con Nuestro Equipo
Datos del proyecto
- País
- Egypt
- Ubicación
- Alexandria
- Año
- 2021 - en curso
- Estado del proyecto
- En curso
Otros proyectos relacionados con esta área
-
Apulia -
TuscanyThe dry dock of the Port of Marina Di Carrara
-
SardiniaConstruction of a Marine Village for yachts and superyachts
-
CalabriaPort of Gioia Tauro
-
Friuli Venezia GiuliaStatic consolidation work on the 'Diga Rizzo Sud' in the Port of Trieste
-
Alexandria CityPort of Abu Qir: New AQCT buildings and interior design
-
ConstantaWaterfront of the city of Constanța
-
LazioPort of Civitavecchia: New Oil Terminal in DEGM area
-
TuscanyNew berths and yard redevelopment for super yachts construction and refitting in the Port of Marina di Carrara
-
Friuli Venezia GiuliaShelter Harbour at the 'Luigi Rizzo Sud' breakwater in the Port of Trieste
-
TuscanyPort of Marina di Carrara: New mooring dolphin for a large cruise ship
-
Friuli Venezia GiuliaPort of Trieste: Renovation of S.I.O.T. Pier
-
Friuli Venezia GiuliaPort of Brindisi: Renovation and reinforcement of the quay
-
Saudi ArabiaPort of Dammam: Hutchison Ports Dammam
-
AbruzzoPort of Ortona: South European Terminal
-
AbruzzoPort of Ortona: Confined disposal facility - New multipurpose terminal
-
EgyptPort of Ain Sokhna (Egypt) - Sokhna Marine Port - Ain Sokhna Port Container Terminal
-
Friuli Venezia GiuliaPort of Trieste: Container Terminal Molo VII – 100 m extension
-
PugliaPort of Taranto (Italy) Redevelopment of the Molo Polisettoriale - Bulk Material Terminal Rehabilitation
-
PugliaPort of Brindisi: Reinforcement of Admiral Millo sailor’s monument and Channel Pigonati
-
PugliaPort of Taranto - Redevelopment of the Molo Polisettoriale of Taranto - New Breakwater
-
PugliaPort of Taranto: Redevelopment of the Molo Polisettoriale of Taranto - Structural investigation of the quay gantry cranes railways
-
LazioPort of Civitavecchia: Maritime and dredging activities connected to TVN Thermal Power Plant